| Clave | Descripción del auxiliar o básico | Unidad |
| CAST0036 | CASTILLO AHOGADO EN HUECO DE BLOCK DE 20 CMS, DE 0.00 A 3.00 MTS DE ALTURA, CON CONCRETO F'C=200 KG/CM2 ARMADO CON UNA VARILLA DE 1/2", INCLUYE: ACARREO, ELEVACION, ARMADO, CONCRETO, MATERIAL, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 01VAR004 | VARILLA CORRUGADA DE 1/2" | KG | 1.1832 | 8.6 | 10.18 |
| 01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.0358 | 18 | 0.64 |
| 06MAD001 | MADERA DE PINO | PT | 0.02 | 10 | 0.2 |
| Suma de Material | 11.02 | ||||
| Mano de Obra | |||||
| MOF05001 | OFICIAL FIERRERO | JOR | 0.01 | 401.97 | 4.02 |
| MOA05003 | AYUDANTE | JOR | 0.02 | 245.43 | 4.91 |
| MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.01786 | 401.97 | 7.18 |
| MOA05004 | P E O N | JOR | 0.01786 | 210.17 | 3.75 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.05 | 19.86 | 0.99 |
| Suma de Mano de Obra | 20.85 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.02 | 19.86 | 0.4 |
| Suma de Herramienta | 0.4 | ||||
| Equipo | |||||
| 90AND001 | ANDAMIOS METÁLICOS UN MODULO | DIA | 0.0234 | 10.21 | 0.24 |
| Suma de Equipo | 0.24 | ||||
| Auxiliar | |||||
| BASIC007 | CONCRETO F'C=200 KG/CM2, T.M.A. 3/4" | M3 | 0.0269 | 1272.72 | 34.24 |
| Suma de Auxiliar | 34.24 | ||||
| Costo Directo | 66.75 |