Clave | Descripción del auxiliar o básico | Unidad |
07-0180 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 15 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON 4 VARILLAS A.R. DE 5/16″ ESTRIBOS DE 1/4″ A/C 30 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106 | 12.74 | 14.09 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 1.1628 | 12.58 | 14.63 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.7379 | 12.55 | 9.26 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.2 | 14.3 | 2.86 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125 | 18.93 | 2.37 |
0950-05 | DIESEL | LT | 0.4 | 5.41 | 2.16 |
Suma de Material | 45.37 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.0851 | 756.84 | 64.41 |
Suma de Mano de Obra | 64.41 | ||||
Concepto | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.0236 | 981.58 | 23.17 |
Suma de Concepto | 23.17 | ||||
Costo Directo | 132.95 |