Clave | Descripción del auxiliar o básico | Unidad |
BASIC003 | CONCRETO F’C=100 KG/CM2, T.M.A. 3/4″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
02CEM000 | CEMENTO GRIS | KG | 300.3 | 2.4 | 720.72 |
03ARE000 | ARENA | M3 | 0.55 | 130.01 | 71.51 |
03GRA000 | GRAVA DE 3/4″ | M3 | 0.748 | 130.01 | 97.25 |
28AGUA00 | AGUA CON PIPA | M3 | 0.24725 | 80 | 19.78 |
Suma de Material | 909.26 | ||||
Auxiliar | |||||
BASIF000 | FABRICACION DE CONCRETO | M3 | 1 | 107.44 | 107.44 |
Suma de Auxiliar | 107.44 | ||||
Costo Directo | 1016.7 |