Clave | Descripción del auxiliar o básico | Unidad |
07-1350 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 15 X 15 CM, CONCRETO F’C=150 KG/CM2-3/4″, REFORZADA CON 4 VARILLAS R.N. DE 3/8″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106 | 12.74 | 14.09 |
0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8″ ) | KG | 2.3394 | 10.43 | 24.4 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.7379 | 12.55 | 9.26 |
0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.2 | 14.23 | 2.85 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125 | 18.93 | 2.37 |
0950-05 | DIESEL | LT | 0.4 | 5.41 | 2.16 |
Suma de Material | 55.13 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.1111 | 756.84 | 84.08 |
Suma de Mano de Obra | 84.08 | ||||
Concepto | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.0236 | 912.5 | 21.54 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.1111 | 22.08 | 2.45 |
Suma de Concepto | 23.99 | ||||
Costo Directo | 163.2 |