| Clave | Descripción del auxiliar o básico | Unidad |
| 020208 | CIMBRA COMUN EN CONTRATRABES DE CIMENTACION DE 25 X 100 CM. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 2.9 | 14.76 | 42.8 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.91 | 14.76 | 28.19 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 1.05 | 5.75 | 6.04 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.09 | 5.48 | 0.49 |
| 0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | KG | 0.001 | 4.03 | 0 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.04 | 6.93 | 0.28 |
| 0950-05 | DIESEL | LT | 0.5 | 4.24 | 2.12 |
| Suma de Material | 79.92 | ||||
| Mano de Obra | |||||
| 02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | JOR | 0.1443 | 571.57 | 82.48 |
| Suma de Mano de Obra | 82.48 | ||||
| Costo Directo | 162.4 |