| Clave | Descripción del auxiliar o básico | Unidad |
| HA174 | Concreto f'c=300 kg/cm2, r.n., tma 19mm (3/4"), hecho en obra c/revolvedora | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| ACACT055 | Cemento Tolteca CPC 30 R (cemento portland compuesto) | t | 0.449 | 1373.91 | 616.89 |
| BAGRE0587 | Arena de rio (cribada) l.a.b. banco | M3 | 0.542 | 36.3 | 19.67 |
| BAGRE0213 | Material p/carpeta 19mm. (3/4") -finos l.a.b. banco | M3 | 0.662 | 45 | 29.79 |
| ACMXX005 | Agua | m3 | 0.253 | 85 | 21.51 |
| Suma de Material | 687.86 | ||||
| Auxiliar | |||||
| HA169 | Elaboracion concreto obra c/revolvedora | m3 | 1 | 174.84 | 174.84 |
| Suma de Auxiliar | 174.84 | ||||
| Costo Directo | 862.7 |