| Clave | Descripción del auxiliar o básico | Unidad |
| CAST0033 | CASTILLO AHOGADO EN HUECO DE BLOCK DE 20 CMS, DE 0.00 A 3.00 MTS DE ALTURA, CON CONCRETO F'C=150 KG/CM2 ARMADO CON UNA VARILLA DE 3/8", INCLUYE: ACARREO, ELEVACION, ARMADO, CONCRETO, MATERIAL, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 01VAR003 | VARILLA CORRUGADA DE 3/8" | KG | 0.6617 | 8.6 | 5.69 |
| 01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.02 | 18 | 0.36 |
| 06MAD001 | MADERA DE PINO | PT | 0.02 | 10 | 0.2 |
| Suma de Material | 6.25 | ||||
| Mano de Obra | |||||
| MOF05001 | OFICIAL FIERRERO | JOR | 0.00556 | 401.97 | 2.23 |
| MOA05003 | AYUDANTE | JOR | 0.01 | 245.43 | 2.45 |
| MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.01786 | 401.97 | 7.18 |
| MOA05004 | P E O N | JOR | 0.01786 | 210.17 | 3.75 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.05 | 15.61 | 0.78 |
| Suma de Mano de Obra | 16.39 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.02 | 15.61 | 0.31 |
| Suma de Herramienta | 0.31 | ||||
| Equipo | |||||
| 90AND001 | ANDAMIOS METÁLICOS UN MODULO | DIA | 0.0234 | 10.21 | 0.24 |
| Suma de Equipo | 0.24 | ||||
| Auxiliar | |||||
| BASIC005 | CONCRETO F'C=150 KG/CM2, T.M.A. 3/4" | M3 | 0.0269 | 1185.15 | 31.88 |
| Suma de Auxiliar | 31.88 | ||||
| Costo Directo | 55.07 |