Clave | Descripción del auxiliar o básico | Unidad |
DALA0134 | DALA DE CERRAMIENTO DE 20 X 25 CMS DE CONCRETO F’C=200 KG/CM2 ARMADO CON 4 VARILLAS DE 3/8″ Y ESTRIBOS DE ALAMBRON DE 1/4″ A CADA 20 CMS, INCLUYE: ARMADO, CIMBRADO, DESCIMBRADO, MATERIALES, FABRICACION DE CONCRETO, COLADO, MANO DE OBRA Y HERRAMIENTA. | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
01VAR003 | VARILLA CORRUGADA DE 3/8″ | KG | 2.40624 | 8.6 | 20.69 |
01ALA005 | ALAMBRON DE 1/4″ | KG | 1.125 | 19 | 21.38 |
01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.10581 | 18 | 1.9 |
06MAD001 | MADERA DE PINO | PT | 1.5 | 10 | 15 |
06CLA001 | CLAVOS | KG | 0.16 | 18 | 2.88 |
13DIE000 | DIESEL | LT | 0.24 | 7 | 1.68 |
Suma de Material | 63.53 | ||||
Mano de Obra | |||||
MOF05001 | OFICIAL FIERRERO | JOR | 0.03527 | 401.97 | 14.18 |
MOA05003 | AYUDANTE | JOR | 0.03527 | 245.43 | 8.66 |
MOC05001 | CARPINTERO DE OBRA | JOR | 0.066 | 401.97 | 26.53 |
MOA05003 | AYUDANTE | JOR | 0.066 | 245.43 | 16.2 |
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.03696 | 401.97 | 14.86 |
MOA05004 | P E O N | JOR | 0.14784 | 210.17 | 31.07 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.05 | 111.5 | 5.58 |
Suma de Mano de Obra | 117.08 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.02 | 111.5 | 2.23 |
Suma de Herramienta | 2.23 | ||||
Equipo | |||||
90AND001 | ANDAMIOS METÁLICOS UN MODULO | DIA | 0.12396 | 10.21 | 1.27 |
Suma de Equipo | 1.27 | ||||
Auxiliar | |||||
BASIC007 | CONCRETO F’C=200 KG/CM2, T.M.A. 3/4″ | M3 | 0.0525 | 1272.72 | 66.82 |
Suma de Auxiliar | 66.82 | ||||
Costo Directo | 250.93 |