| Clave | Descripción del auxiliar o básico | Unidad |
| CAST0015 | CASTILLO AHOGADO EN HUECO DE BLOCK DE 12 CMS, DE 0.00 A 3.00 MTS DE ALTURA, CON CONCRETO F'C=150 KG/CM2 SIMPLE (SIN ARMADO), INCLUYE: ACARREO, CONCRETO, MATERIAL, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Mano de Obra | |||||
| MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.025 | 401.97 | 10.05 |
| MOA05004 | P E O N | JOR | 0.025 | 210.17 | 5.25 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.05 | 15.3 | 0.77 |
| Suma de Mano de Obra | 16.07 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.02 | 15.3 | 0.31 |
| Suma de Herramienta | 0.31 | ||||
| Auxiliar | |||||
| BASIC005 | CONCRETO F'C=150 KG/CM2, T.M.A. 3/4" | M3 | 0.01065 | 1185.15 | 12.62 |
| Suma de Auxiliar | 12.62 | ||||
| Costo Directo | 29 |