| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO 175 KG/CM2 | CONCRETO DE 175 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.350000 | $1,565.00 | $547.75 |
| Suma de Material | $547.75 | ||||
| Mano de Obra | |||||
| 1ALBAÑIL+6AYUD | 1ALBAÑIL+6AYUDANTES+1/10 CABO | jor | 0.060000 | $2,244.53 | $134.67 |
| Suma de Mano de Obra | $134.67 | ||||
| Equipo | |||||
| REVOLVEDORA 1S | REVOLVEDORA DE 1 SACO MOTOR KHOLER 8 HP | HR | 0.300030 | $10.47 | $3.14 |
| Suma de Equipo | $3.14 | ||||
| Otros | |||||
| GRAVA DE BANCO | GRAVA DE BANCO | M3 | 0.650000 | $79.53 | $51.69 |
| AGUA INCLUYE ACARR | AGUA INCLUYE ACARREO | M3 | 0.200000 | $51.08 | $10.22 |
| ARENA DE BANCO | ARENA DE BANCO | M3 | 0.470000 | $74.68 | $35.10 |
| Suma de Otros | $97.01 | ||||
| Costo Directo | $782.57 |