| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA APARENTE EN L | cimbra aparente en losas y prelosas | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY16 MM | CIMBRAPLAY DE 16MM EN M2 | M2 | 0.200000 | $96.00 | $19.20 |
| MADERA DE PINO 3A | MADERA DE PINO 3A | PT | 4.250000 | $7.50 | $31.88 |
| CIMBRA05 | CLAVO (VARIAS MED.) | Kg | 0.130000 | $16.25 | $2.11 |
| DESMOLTANTESIKA | DESMOLDANTE SEPAROL DE SIKA EN LTS | LT | 0.400000 | $13.80 | $5.52 |
| ALAMBRE | ALAMBRE RECOCIDO | KG | 0.050000 | $13.00 | $0.65 |
| ACERO REF. NO.2 | ACERO DE REFUERZO DE No.2 | KG | 0.700000 | $12.00 | $8.40 |
| Suma de Material | $67.76 | ||||
| Mano de Obra | |||||
| CUAD OC 08 | CUADRILLA OC 08 (1 OF. CARPINTERO O.N. + 1AYTE.) | JOR | 0.125000 | $910.74 | $113.84 |
| Suma de Mano de Obra | $113.84 | ||||
| Otros | |||||
| ANDAMIO | ANDAMIO RENTA POR DIA | DIA | 0.250000 | $71.19 | $17.80 |
| Suma de Otros | $17.80 | ||||
| Costo Directo | $199.40 |