| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO 150 19MM | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4 HECHO EN OBRA" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.326000 | $1,500.00 | $489.00 |
| ARENA | ARENA | M3 | 0.536000 | $90.00 | $48.24 |
| GRAVA DE 3/4" | GRAVA DE 3/4" | M3 | 0.650000 | $200.00 | $130.00 |
| AGUA | AGUA | M3 | 0.243600 | $50.00 | $12.18 |
| Suma de Material | $679.42 | ||||
| Costo Directo | $679.42 |