| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONC.H/OF-C=100RN3/4 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2 RESISTENCIA NORMAL. AGREGADO MAXIMO 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.273000 | $1,600.00 | $436.80 |
| ARENA | ARENA PARA CONSTRUCCION | M3 | 0.542000 | $180.00 | $97.56 |
| GRAVA 3/4" | GRAVA DE 3/4" | M3 | 0.650000 | $190.00 | $123.50 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.263000 | $50.00 | $13.15 |
| Suma de Material | $671.01 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 05 | CUADRILLA NO. 5 (1 OPERADOR + 7 PEONES) | JOR | 0.055000 | $2,383.13 | $131.07 |
| Suma de Mano de Obra | $131.07 | ||||
| Equipo | |||||
| REVOLVEDORA 8 H.P. | Revolvedora Kohler sin operador. | HR | 1.000000 | $65.76 | $65.76 |
| Suma de Equipo | $65.76 | ||||
| Costo Directo | $867.84 |