| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CON250 T Y L H EN O | CONCRETO F'C= 250 KG/CM2 EN TRABES Y LOSAS HECHO EN OBRA | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0063-9 | CONCRETO F'C=250 KG/CM2 | M3 | 1.050000 | $720.36 | $756.38 |
| Suma de Material | $756.38 | ||||
| Mano de Obra | |||||
| 0001-9 | PEÓN | jor | 1.250000 | $163.09 | $203.86 |
| 0004-3 | OFICIAL DE ALBAÑILERÍA | jor | 0.300000 | $297.35 | $89.21 |
| Suma de Mano de Obra | $293.07 | ||||
| Herramienta | |||||
| 0000-0 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $293.07 | $8.79 |
| Suma de Herramienta | $8.79 | ||||
| Equipo | |||||
| REVOLVEDORA | REVOLVEDORA PARA CONCRETO MIPSA-KOHLER R-10 8 H.P. 1 SACO | Hora | 1.000000 | $43.24 | $43.24 |
| VIBRADOR PARA CONCRE | VIBRADOR PARA CONCRETO | Hora | 0.500000 | $37.31 | $18.66 |
| Suma de Equipo | $61.90 | ||||
| Costo Directo | $1,120.14 |