| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-GUARN | CIMBRA PARA GUARNICON DE 15x30 CM. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA DE PINO 3202 | MADERA DE PINO DE 3a, DE 2" X 4" X 8.25' | P.T. | 1.375000 | $9.20 | $12.65 |
| MADERA DE PINO 3196 | MADERA DE PINO DE 3a. DE 1" X 2" X 8.25' | P.T. | 3.006660 | $9.20 | $27.66 |
| CLAVO DE 1 1/2" | CLAVO DE 1 1/2" | KG. | 0.385200 | $14.37 | $5.54 |
| 0950-05 | DIESEL | LT | 0.600000 | $5.80 | $3.48 |
| Suma de Material | $49.33 | ||||
| Mano de Obra | |||||
| CARPINTERO | CARPINTERO DE OBRA NEGRA. | Jor. | 0.083330 | $248.00 | $20.66 |
| AYUDANTE | AYUDANTE. | JOR | 0.083330 | $199.89 | $16.65 |
| CABO | CABO DE CUADRILLA | Jor. | 0.008330 | $412.60 | $3.42 |
| Suma de Mano de Obra | $40.73 | ||||
| Herramienta | |||||
| HERRAM | HERRAMIENTA MENOR | (%)mo | 0.030000 | $40.73 | $1.22 |
| Suma de Herramienta | $1.22 | ||||
| Costo Directo | $91.28 |