| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA | CIMBRA DE CONTACTO PARA ELEMNTOS DE CONCRETO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA-002 | MADERA DE PINO DE 4" X 4" X 4.87 | PT | 2.500000 | $7.50 | $18.75 |
| ALAMBRON 1/4" | ALAMBRON DE 1/4" | kg | 0.250000 | $9.85 | $2.46 |
| CIMBRA-003 | CLAVO DE 2 1/2" A 4 1/2" | KG | 0.020000 | $13.04 | $0.26 |
| COMBUSTIBLE 01 | DIESEL | LT | 1.000000 | $6.50 | $6.50 |
| CIMBRA-001-01 | CIMBRAPLAY | M2 | 0.200000 | $100.67 | $20.13 |
| Suma de Material | $48.10 | ||||
| Mano de Obra | |||||
| CUADRILLA CARO. ON | (1 Of. Carpintero O.N. + 1Ayte). | JOR | 0.100000 | $748.68 | $74.87 |
| Suma de Mano de Obra | $74.87 | ||||
| Costo Directo | $122.97 |