| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| SCT-AUX-CIMB-02 | Cimbra para cunetas y lavaderos | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-FERR-01 | Clavo de 2½" a 4" | kg | 0.050000 | $20.00 | $1.00 |
| SCT-MAT-MAD-02 | Triplay de 1.22 x 2.44 m 16 mm 1 cara | m2 | 1.000000 | $107.38 | $107.38 |
| SCT-MAT-COMB-01 | Diesel | lt | 1.000000 | $8.70 | $8.70 |
| Suma de Material | $117.08 | ||||
| Mano de Obra | |||||
| SCT-CUA-08 | Cuadrilla (1 Carpintero + 1 Ayudante) | Jor | 0.070000 | $928.57 | $65.00 |
| Suma de Mano de Obra | $65.00 | ||||
| Herramienta | |||||
| SCT-HERR-01 | Herramienta menor | (%)mo | 0.020000 | $65.00 | $1.30 |
| SCT-HERR-02 | Seguridad industrial | (%)mo | 0.020000 | $65.00 | $1.30 |
| Suma de Herramienta | $2.60 | ||||
| Costo Directo | $184.68 |