| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BAS-MAD09 | TARIMA DE MADERA SECCION 0.50x2.44 | pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAD001: | TRIPLAY DE 16 mm. HOJA DE 1.22x2.44 | pieza | 0.003022 | $325.00 | $0.98 |
| C1 | Barrote 1 1/2 x 4 x 8 | pt | 1.458300 | $13.83 | $20.17 |
| C8 | Duela 3/4 x 4 x 8 | pt | 2.283300 | $16.02 | $36.58 |
| CLAVO1 | CLAVO DE 2 1/2" A 3 1/2" | kg | 0.136800 | $17.84 | $2.44 |
| CLAVO1 | CLAVO DE 2 1/2" A 3 1/2" | kg | 0.210000 | $17.84 | $3.75 |
| ALAMBRON | ALAMBRON LISO DE 1/4" ( NO. 2 ) | ton | 0.001800 | $15,950.00 | $28.71 |
| Suma de Material | $92.63 | ||||
| Mano de Obra | |||||
| A02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | jor | 0.040000 | $784.69 | $31.39 |
| Suma de Mano de Obra | $31.39 | ||||
| Equipo | |||||
| 03-6030 | SIERRA DE BANCO PARA MADERA | hora | 0.320000 | $14.13 | $4.52 |
| Suma de Equipo | $4.52 | ||||
| Costo Directo | $128.54 |