| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CE-02-01 | CIMBRA COMUN ZAPATAS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP035 | barrote 1 1/2" x 4" x 8' | PT | 2.500000 | $5.62 | $14.05 |
| CIAMP055 | duela 3/4" x 4" x 8' | PT | 2.000000 | $7.52 | $15.04 |
| CIMBRA-02 | CLAVO | Kg. | 0.090000 | $17.10 | $1.54 |
| DIESEL | DESMOLDANTE | Lt | 0.500000 | $6.10 | $3.05 |
| A4BAR012 | alambre recocido cal. 18 | KG | 0.045000 | $11.54 | $0.52 |
| Suma de Material | $34.20 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.086957 | $736.93 | $64.08 |
| Suma de Mano de Obra | $64.08 | ||||
| Costo Directo | $98.28 |