| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA APARENTE 2 | CIMBRA APARENTE EN LOSA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 6.000000 | $16.15 | $96.90 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.100000 | $34.00 | $3.40 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| TRIPLAY 16 MM 1 | TRIPLAY DE PINO DE 16 MM DE ESPESOR | M2 | 0.300000 | $112.00 | $33.60 |
| Suma de Material | $139.54 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.016500 | $290.45 | $4.79 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.165000 | $233.90 | $38.59 |
| AYUDANTE OPERADOR 1 | AYUDANTE OPERADOR | JOR | 0.165000 | $186.17 | $30.72 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.165000 | $169.01 | $27.89 |
| Suma de Mano de Obra | $101.99 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $101.99 | $3.06 |
| Suma de Herramienta | $3.06 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.050000 | $200.73 | $10.04 |
| Suma de Equipo | $10.04 | ||||
| Costo Directo | $254.63 |