| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA APARENTE EN T | CIMBRA APARENTE EN TRABES | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP110 | cimbra imp 1.22x2.44m 16mm 1c | M2 | 0.057400 | $92.14 | $5.29 |
| CIAMP090 | polin de 3 1/2"x3 1/2" regular | PT | 3.157500 | $9.80 | $30.94 |
| CIAMP035 | barrote 1 1/2" x 4" x 8' | PT | 1.205000 | $5.62 | $6.77 |
| CIAMP045 | chaflan de 3/4" x 8' | ML | 1.100000 | $2.00 | $2.20 |
| CIAMP055 | duela 3/4" x 4" x 8' | PT | 1.830000 | $7.52 | $13.76 |
| CIMBRA-02 | CLAVO | Kg. | 0.563800 | $17.10 | $9.64 |
| A4BAR012 | alambre recocido cal. 18 | KG | 0.144300 | $11.54 | $1.67 |
| DIESEL | DESMOLDANTE | Lt | 0.610000 | $6.10 | $3.72 |
| Suma de Material | $73.99 | ||||
| Mano de Obra | |||||
| CUA CARPINTERO 2 | (1 Oficial carpintero de obra negra + 1 ayte.) | JOR | 0.090909 | $733.32 | $66.67 |
| Suma de Mano de Obra | $66.67 | ||||
| Costo Directo | $140.66 |