| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CHE-CONCRETO200 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-AGLUT-02 | AGUA POTABLE | m3 | 0.202000 | $12.00 | $2.42 |
| CHE-AGLUT-04 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.348000 | $1,637.93 | $570.00 |
| CHE-AGREGADO-02 | ARENA RIO | M3 | 0.555000 | $150.00 | $83.25 |
| CHE-AGREGADO-01 | GRAVA | M3 | 0.630000 | $228.27 | $143.81 |
| Suma de Material | $799.48 | ||||
| Mano de Obra | |||||
| CUA-CHE-20 | CUADRILLA ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 5 PEONES ) | JOR | 0.100000 | $2,779.31 | $277.93 |
| Suma de Mano de Obra | $277.93 | ||||
| Equipo | |||||
| CHE-EQUIPO-024 | REVOLVEDORA MIPSA-KOHLER R-10 8 H.P. 1 SACO | HR | 0.533300 | $25.99 | $13.86 |
| Suma de Equipo | $13.86 | ||||
| Costo Directo | $1,091.27 |