| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BAS-CIM | CIMBRA DE MADERA DE PINO DE 3a. ACABADO COMUN EN ESTRUCTURA, INCLUYE: MATERIALES, ACARREOS, DESPERDICIOS, HABILITADO, OBRA FALSA, CIMBRADO, DESCIMBRADO Y LIMPIEZA (POR SUPERFICIE DE CONTACTO), P.U.O.T. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY 16 MM. | cimbraplay de contacto de 16 mm. | M2 | 0.125000 | $65.00 | $8.13 |
| CLAVO CON CABEZA DE | Clavo con cabeza de 3" .004KG/PZA PROM. | kg | 0.080000 | $16.12 | $1.29 |
| DIESEL | diesel | Lt | 0.400000 | $5.50 | $2.20 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 1.200000 | $6.20 | $7.44 |
| POLÍN 3 1/2 X 3 1/2" | Polín 3 1/2 x 3 1/2" x 8 1/4' | pt | 0.572500 | $5.00 | $2.86 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.120000 | $10.12 | $1.21 |
| Suma de Material | $23.13 | ||||
| Mano de Obra | |||||
| CUADRILLA-SAMS-06 | 1 OFICIAL CARPINTERO + 1 AYUDANTE | JOR | 0.058824 | $676.96 | $39.82 |
| Suma de Mano de Obra | $39.82 | ||||
| Costo Directo | $62.95 |