| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.5CON | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 20MM, FABRICADO EN OBRA POR MEDIOS MECANICOS, INCLUYE: ACARREO DE MATERIAL A 1A. ESTACION DE 20.00 M. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| C03 | CEMENTO PORTLAND GRIS SACO | TON | 0.306000 | $2,097.00 | $641.68 |
| AGR01 | ARENA (MATERIAL PÉTREO) | M3 | 0.580000 | $79.66 | $46.20 |
| AGR04 | GRAVA TRITURADA DE 3/4" | M3 | 0.630000 | $105.41 | $66.41 |
| AG | AGUA EN PIPA | M3 | 0.202000 | $51.50 | $10.40 |
| Suma de Material | $764.69 | ||||
| Mano de Obra | |||||
| ZCUAD3 | CUADRILLA (CONFORMADA POR 5 PEONES) | JOR | 0.066700 | $2,380.40 | $158.77 |
| Suma de Mano de Obra | $158.77 | ||||
| Equipo | |||||
| 25MAQ | Revolvedora ARSI:AR-10EK 1 saco de 8 hp mot. Kohler s/reductor | Hora | 0.533299 | $104.85 | $55.92 |
| Suma de Equipo | $55.92 | ||||
| Costo Directo | $979.38 |