| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AUX-PV01 | FIRME DE CONCRETO F'C= 200 KG/CM2 DE 0.15 M. DE ESPESOR Y ARMADO CON VS. DEL No. 3 @ 20 CMS. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP090 | Polin de 3 1/2"x3 1/2" regular | pt | 3.105882 | $6.77 | $21.03 |
| DIESEL | DIESEL | LT | 0.044118 | $5.06 | $0.22 |
| Suma de Material | $21.25 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 2 (1 albañil + 1 peon) | JOR | 0.045455 | $675.54 | $30.71 |
| Suma de Mano de Obra | $30.71 | ||||
| Otros | |||||
| 11800-02 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4", ELABORADO CON REVOLVEDORA. | M3 | 0.153000 | $827.76 | $126.65 |
| Suma de Otros | $126.65 | ||||
| Costo Directo | $178.61 |