| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONC. F-C=150KG/CM2. | CONCRETO HECHO EN OBRA F'C=150 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONS006 | CEMENTO GRIS PORTLAND | TON | 0.326000 | $1,671.17 | $544.80 |
| CONS002 | ARENA DE LA REGION | M3 | 0.536000 | $257.00 | $137.75 |
| GRAVA | GRAVA | M3 | 0.650000 | $291.23 | $189.30 |
| CONS001 | AGUA PUESTA EN OBRA EN PIPA | M3 | 0.251000 | $19.77 | $4.96 |
| Suma de Material | $876.81 | ||||
| Mano de Obra | |||||
| CUAD031 | CUADRILLA PARA ELABORACION DE CONCRETO | jor | 0.066670 | $2,071.08 | $138.08 |
| Suma de Mano de Obra | $138.08 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $138.08 | $5.52 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $138.08 | $2.76 |
| Suma de Herramienta | $8.28 | ||||
| Otros | |||||
| MAQ016 | EQUIPO REVOLVEDORA | hora | 0.666700 | $19.24 | $12.83 |
| Suma de Otros | $12.83 | ||||
| Costo Directo | $1,036.00 |