| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ELEMENTOS SEC. | ELEMENTOS SEC. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CANAL ESTRUCTURAL | CANAL ESTRUCTURAL | KG | 0.542500 | $8.75 | $4.75 |
| PLACA A-36 | PLACA A-36 | KG | 0.542500 | $8.50 | $4.61 |
| GAS P/ CORTES | GAS P/ CORTES | KG | 0.009000 | $8.69 | $0.08 |
| OXIGENO | OXIGENO | M3 | 0.010560 | $19.00 | $0.20 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.010000 | $35.00 | $0.35 |
| ALAMBRE TUBULAR | ALAMBRE TUBULAR | KG | 0.015000 | $34.50 | $0.52 |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002000 | $36.90 | $0.07 |
| GALVANIZADO | GALVANIZADO | KG | 1.085000 | $8.50 | $9.22 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.043821 | $19.80 | $0.87 |
| Suma de Material | $20.67 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.003421 | $545.84 | $1.87 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.003420 | $545.84 | $1.87 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.004142 | $1,142.20 | $4.73 |
| Suma de Mano de Obra | $8.47 | ||||
| Equipo | |||||
| EQUIPO DE OXICORTE | Equipo de corte oxigeno-gas | HR | 0.013880 | $1.14 | $0.02 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $2.11 | $0.06 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.011440 | $8.74 | $0.10 |
| Suma de Equipo | $0.18 | ||||
| Costo Directo | $29.32 |