| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCR 02 | CONCRETO HIDRAULICO HECHO EN OBRA TMA 3/4" F'C=150 KG/CM2 | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGLUT 01 | CEMENTO PORTLAND GRIS | ton | 0.330018 | $1,750.00 | $577.54 |
| AGREG 01 | ARENA DE MINA PUESTA EN OBRA | m3 | 0.548733 | $140.00 | $76.82 |
| AGREG 02 | GRAVA LIMPIA PUESTA EN OBRA | m3 | 0.657864 | $190.00 | $124.99 |
| AGUA | AGUA PUESTA EN OBRA | M3 | 0.260681 | $120.00 | $31.28 |
| Suma de Material | $810.63 | ||||
| Equipo | |||||
| EQ MENOR 02 | REVOLVEDORA DE 1 SACO MARCA ARSI | hora | 0.930000 | $75.93 | $70.61 |
| Suma de Equipo | $70.61 | ||||
| Otros | |||||
| CUAD 08 | CUADRILLA 08 (ALBAÑIL + 6 AYUDANTES) | jor | 0.100000 | $2,087.74 | $208.77 |
| Suma de Otros | $208.77 | ||||
| Costo Directo | $1,090.01 |