| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-PINTURA-01 | PINTURA ESMALTE COMEX 100 | LT | 0.450000 | $78.31 | $35.24 |
| CHE-PINTURA-02 | THINNER 48 SOLIDOS | LT | 0.340000 | $20.94 | $7.12 |
| CHE-VAR-06 | ESTOPA | kg | 0.100000 | $12.00 | $1.20 |
| CHE-PINTURA-14 | PLASTER PARA DAR ACABADO | LT | 0.080000 | $112.17 | $8.97 |
| CHE-PINTURA-15 | CEPILLO DE ALAMBRE DEL NO. 18 | PZA | 0.140000 | $17.39 | $2.43 |
| CHE-PINTURA-17 | BROCHA NORTEÑA 2" | PZA | 0.033330 | $11.02 | $0.37 |
| Suma de Material | $55.33 | ||||
| Mano de Obra | |||||
| CUA-CHE-08 | CUADRILLA ( 1 PINTOR + 1 AYUDANTE ) | JOR | 0.050000 | $997.67 | $49.88 |
| Suma de Mano de Obra | $49.88 | ||||
| Equipo | |||||
| CHE-EQUIPO-029 | Equipo de pintura IPSA | HR | 0.209000 | $3.20 | $0.67 |
| Suma de Equipo | $0.67 | ||||
| Otros | |||||
| AND006 | ANDAMIO DE ACERO TUBULAR DE 4.00M. DE ALTURA CON RUEDAS Y BASE DE TABLONES DE MADERA. | R/D | 0.050000 | $76.59 | $3.83 |
| Suma de Otros | $3.83 | ||||
| Costo Directo | $109.71 |