| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO 300 3/4" | CONCRETO Fc= 300 KG/CM2, RESISTENCIA NORMAL, T.M.A. 19 mm HECHO EN OBRA | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GRAVA DE 3/4" | GRAVA DE 3/4" | M3 | 0.650000 | $175.00 | $113.75 |
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.500000 | $1,440.00 | $720.00 |
| ARENA | ARENA | M3 | 0.550000 | $75.00 | $41.25 |
| AGUA | AGUA | M3 | 0.270000 | $19.00 | $5.13 |
| Suma de Material | $880.13 | ||||
| Costo Directo | $880.13 |