| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020225 | CIMBRA EN LOSAS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 3.190000 | $16.00 | $51.04 |
| TRIP16 | TRIPLAY DE PINO 16 MM UNA CARA | M2 | 0.250000 | $112.00 | $28.00 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.260000 | $9.00 | $2.34 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 2.040000 | $7.00 | $14.28 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.350000 | $18.00 | $6.30 |
| 0950-05 | DIESEL | LT | 0.700000 | $6.00 | $4.20 |
| Suma de Material | $106.16 | ||||
| Mano de Obra | |||||
| 02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | JOR | 0.117600 | $799.62 | $94.04 |
| Suma de Mano de Obra | $94.04 | ||||
| Costo Directo | $200.20 |