| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMIENTO DE MAMPOST | MAMPOSTERIA DE 3A CLASE | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDRA BRASA | PIEDRA BRASA | M3 | 1.600000 | $120.00 | $192.00 |
| Suma de Material | $192.00 | ||||
| Mano de Obra | |||||
| 1ALBAÑIL+2PEONES | 1 ALBAÑIL+2PEON+1/10 CABO | jor | 0.200000 | $1,053.59 | $210.72 |
| Suma de Mano de Obra | $210.72 | ||||
| Otros | |||||
| MORTERO 1:5 | MORTERO 1:5 | M3 | 0.320000 | $977.65 | $312.85 |
| TARIFA 1ER KM | TARIFA 1ER KM | M3 | 1.600000 | $3.86 | $6.18 |
| TARIFA KM SUB AL 1ER | TARIFA KM SUBSECUENTES AL 1ER KM | M3-KM | 14.400000 | $2.88 | $41.47 |
| Suma de Otros | $360.50 | ||||
| Costo Directo | $763.22 |