| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS 1 | CEMENTO GRIS NORMAL | TON | 0.274000 | $2,378.40 | $651.68 |
| ARENA M ALEMAN 1 | ARENA MIGUEL ALEMAN | M3 | 0.475000 | $315.00 | $149.63 |
| GRAVA M ALEMAN 1 | GRAVA MIGUEL ALEMAN | M3 | 0.725000 | $310.00 | $224.75 |
| AGUA ADQUIRIDA 1 | AGUA ADQUIRIDA | M3 | 0.200000 | $31.50 | $6.30 |
| Suma de Material | $1,032.36 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006940 | $290.45 | $2.02 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.069440 | $233.90 | $16.24 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.069440 | $181.41 | $12.60 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.416670 | $169.01 | $70.42 |
| Suma de Mano de Obra | $101.28 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $101.28 | $3.04 |
| Suma de Herramienta | $3.04 | ||||
| Equipo | |||||
| REVOLVEDORA 1 SACO 1 | REVOLVEDORA KOHLER R-10 DE 1 SACO MOTOR GASOLINA DE 8 HP | HORA | 0.444440 | $47.29 | $21.02 |
| CAMION PLATAF 6.8T 1 | CAMION PLATAFORMA FORD DE 6.8 TON DE CAPACIDAD | HORA | 0.055560 | $239.29 | $13.29 |
| Suma de Equipo | $34.31 | ||||
| Costo Directo | $1,170.99 |