| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| SCT-AUX-23 | CIMBRADO DE FRONTERA CON CIMBRA METALICA. INCLUYE CONSUMOS, RENTA DE CIMBRA Y MANO DE OBRA | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-ACER-04 | VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) | ton | 0.000040 | $9,900.00 | $0.40 |
| SCT-MAT-ACER-01 | Alambre recocido no. 16 | kg | 0.038180 | $16.50 | $0.63 |
| SCT-MAT-COMB-01 | Diesel | lt | 0.056770 | $10.10 | $0.57 |
| Suma de Material | $1.60 | ||||
| Mano de Obra | |||||
| SCT-CUA-08 | Cuadrilla (1 carpintero + 1 ayudante) | Jor | 0.038420 | $970.76 | $37.30 |
| Suma de Mano de Obra | $37.30 | ||||
| Otros | |||||
| SCT-AUX-04 | SUMINISTRO, FABRICACION Y MONTAJE DE ESTRUCTURA METALICA MEDIANA A BASE DE PLACA DE ACERO A-36 DE 3/16" (37.35 KG/M2) INCLUYE: MATERIAL, CORTES, DESPERDICIOS, SOLDADURA CON ELECTRODOS E-70, CONSUMO DE ENERGIA ELECTRICA, CONSUMO DE MATERIALES, EQUIPO Y MANO DE OBRA. | kg | 40.338000 | $35.58 | $1,435.23 |
| Suma de Otros | $1,435.23 | ||||
| Costo Directo | $1,474.13 |