| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BASSELLO | RIEGO DE SELLO CON MATERIAL PETREO TIPO3-E | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AC20 | CEMENTO ASFALTICO AC.20 | KG | 36.000000 | $5.96 | $214.56 |
| CRR2P | EMULSION ASFALTICA CAT. CRR-2P | LT | 116.000000 | $6.82 | $791.12 |
| FLEMU | FLETE DE EMULSION | LT | 116.000000 | $0.10 | $11.60 |
| FLETEAC20 | FLETE DE CEMENTO AC-20 | KG | 36.000000 | $0.05 | $1.80 |
| Suma de Material | $1,019.08 | ||||
| Mano de Obra | |||||
| MOM3 | CABO DE OFICIOS | jor | 0.001000 | $311.45 | $0.31 |
| MO09 | OBRERO GENERAL | jor | 0.030000 | $209.51 | $6.29 |
| Suma de Mano de Obra | $6.60 | ||||
| Herramienta | |||||
| HERRAMIENTA | HERRAMIENTA MENOR | (%)mo | 0.050000 | $6.60 | $0.33 |
| EQ.SEG | EQUIPO DE SEGURIDAD | (%)mo | 0.030000 | $6.60 | $0.20 |
| Suma de Herramienta | $0.53 | ||||
| Equipo | |||||
| EQADM | PLANTA DE MEZCLA EN CALIENTE MARCA ADM DE 110 TN/HR, INCLUYE: PLANTA ALIMENTADORA DE LUZ, Y COSTO DE INSTALACION DE LA MISMA, 215 HP | hora | 0.035000 | $2,518.66 | $88.15 |
| EQSI | EQUIPO COMPUTARIZADO PARA APLICACION DE RIEGO DE SELLO SINCRONIZADO TIPO CHEAPSEALER 40 MARCA KAISER DE 180 HP | hora | 0.004000 | $565.99 | $2.26 |
| EQ0008 | COMPACTADOR SOBRE NEUMATICOS MCA. DYNAPAC CP221 DE 100HP ANCHO DE RODADO 1.83 M | hora | 0.010000 | $351.97 | $3.52 |
| EQ0003 | COMPACTADOR DE RODILLO LISO DYNAPAC CA301d DE 135 HP DE 2.13 m TAMBOR Y PESO DE 14 TN | hora | 0.010000 | $451.31 | $4.51 |
| EQ0027 | TANQUE DE ALMACENAMIENTI TIPO PETROLERO, SATEÑA CAP. 40,000 LTS CON QUEMADORES | hora | 0.020000 | $105.85 | $2.12 |
| EQBAR | BARREDORA ROTATORIA AUTOPROPULSADA 90 HP CON FILAMENTO MODELO V35 MARCA CATERPILLAR | hora | 0.008000 | $275.75 | $2.21 |
| EQ00008 | CARGADOR FRONTAL 966-C DE 190 HP | hora | 0.006000 | $528.02 | $3.17 |
| Suma de Equipo | $105.94 | ||||
| Otros | |||||
| BASSELLO3-E | SUMINISTRO, EXTRACCION, TRITURADO Y CRIBADO, DE MATERIAL PETREO TIPO 3-E | M3 | 1.000000 | $94.56 | $94.56 |
| ACAR1 | ACARREO EN CAMION DE VOLTEO DEL 1er KM SOBRE TERRACERIAS | M3 | 1.000000 | $8.53 | $8.53 |
| ACAR5 | ACARREO EN KM SUBSECUENTE DEL KM 2 AL 20 | m3 | 2.000000 | $5.77 | $11.54 |
| Suma de Otros | $114.63 | ||||
| Costo Directo | $1,246.78 |