| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM0003 | Cimbra común en albañileria | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP090 | Polin de 3 1/2"x3 1/2" regular | pt | 0.450500 | $20.58 | $9.27 |
| CIAMP035 | Barrote 1 1/2" x 4" x 8' | pt | 1.860500 | $14.83 | $27.59 |
| CIAMP055 | Duela 3/4" x 4" x 8' | pt | 2.090500 | $17.02 | $35.58 |
| A4EAR020 | Clavo c/cabeza de 2"-4" | kg | 0.324300 | $10.13 | $3.29 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.057200 | $19.00 | $1.09 |
| A1AAR015 | Alambron 1/4" No. 2 | t | 0.001700 | $8,261.87 | $14.05 |
| H7BPL005 | Diesel | L | 1.100000 | $6.16 | $6.78 |
| Suma de Material | $97.65 | ||||
| Mano de Obra | |||||
| JOGP023 | Cuadrilla de carpinteros para cimbras. Incluye : carpintero, ayudante, cabo y herramienta. | jor | 0.100500 | $639.63 | $64.28 |
| Suma de Mano de Obra | $64.28 | ||||
| Costo Directo | $161.93 |