| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CON250 | CONCRETO HIDRAULICO F'C= 250 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO CPO-30RS | CEMENTO TIPO CPO-30RS, PORTLAND TIPO II MCA. MAYA | ton | 0.402700 | $2,200.00 | $885.94 |
| ARENA | ARENA DE BANCO | m3 | 0.460100 | $160.00 | $73.62 |
| GRAVA | GRAVA DE 3/4" | M3 | 0.729700 | $260.00 | $189.72 |
| Suma de Material | $1,149.28 | ||||
| Mano de Obra | |||||
| CUAD.ELABORACION CO | CUADRILLA PARA ELABORACION DE MEZCLAS Y CONCRETOS | JOR | 0.166667 | $2,600.78 | $433.47 |
| Suma de Mano de Obra | $433.47 | ||||
| Herramienta | |||||
| D-HERRAMIENTA MENOR | HERRAMIENTA MENOR | (%)mo | 0.030000 | $433.47 | $13.00 |
| EQUIPO DE SEGURIDAD | EQUIPO DE SEGURIDAD PERSONAL REQUERIDO DEACUERDO AL ANEXO "SI" | (%)mo | 0.030000 | $433.47 | $13.00 |
| Suma de Herramienta | $26.00 | ||||
| Equipo | |||||
| REVOL 1 SACO | REVOLVEDORA 1 SACO MCA MIPSA KHOLER DE 8 H.P. | HORA | 0.533300 | $29.22 | $15.58 |
| Suma de Equipo | $15.58 | ||||
| Costo Directo | $1,624.33 |