| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA | CIMBRA EN CIMENTACION | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | TRIPLAY DE 3/4" 2.44 x 1.22 m. | M2 | 0.250000 | $114.00 | $28.50 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.090000 | $23.38 | $2.10 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.420000 | $6.00 | $20.52 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| ACERO-18 | ALAMBRE RECOCIDO | Kg | 0.350000 | $14.87 | $5.20 |
| Suma de Material | $61.32 | ||||
| Mano de Obra | |||||
| CUADRILLA CARO. ON | (1 Of. Carpintero O.N. + 1Ayte). | JOR | 0.100000 | $530.80 | $53.08 |
| Suma de Mano de Obra | $53.08 | ||||
| Costo Directo | $114.40 |