| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRET F-C=100 19MM | CONCRETO F'c=100 KG/CM2, RESISTENCIA NORMAL, T.M.A. 19 MM HECHO EN OBRA | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARENA | ARENA | M3 | 0.550000 | $100.00 | $55.00 |
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.300000 | $1,690.00 | $507.00 |
| GRAVA DE 3/4" | GRAVA DE 3/4" | M3 | 0.750000 | $200.00 | $150.00 |
| AGUA | AGUA | M3 | 0.250000 | $40.00 | $10.00 |
| Suma de Material | $722.00 | ||||
| Costo Directo | $722.00 |