| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PULIDO | ACABADO PULIDO INTEGRAL EN PISOS DE CONCRETO, INCLUYE:,: ACARREOS, MATERIAL NECESARIO, MEZCLAS, APLICACIÓN. P.U.O.T | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-AGLU-002 | Cemento Normal Tolteca | TON | 0.001500 | $1,902.59 | $2.85 |
| OC-AGREGADO-003 | AGUA | M3 | 0.000450 | $40.00 | $0.02 |
| OC-ADHESIVO FESTER | Adhesivo tipo festerbond | litro | 0.025000 | $55.60 | $1.39 |
| OC-CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ml | 0.001430 | $82.38 | $0.12 |
| OC-PEINE METAL | PEINE METALICO PARA ACABADO DE CONCRETO | pza | 0.000500 | $800.00 | $0.40 |
| Suma de Material | $4.78 | ||||
| Mano de Obra | |||||
| OC-CUA8 | CUADRILLA (1 ALBAÑIL + 1 PEON) | JOR | 0.033460 | $963.50 | $32.24 |
| Suma de Mano de Obra | $32.24 | ||||
| Equipo | |||||
| OC-EQUIPO 1 | REGLA VIBRATORIA | Hora | 0.003571 | $211.07 | $0.75 |
| OC-EQUIPO 2 | ALLANADORA MECANICA CON ASPAS | Hora | 0.016665 | $107.51 | $1.79 |
| Suma de Equipo | $2.54 | ||||
| Costo Directo | $39.56 |