| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| FCO-0150-00 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2 TMA 19 MM | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAAGL001 | CEMENTO TIPO CPO 30-RS | TON | 0.326000 | $1,650.00 | $537.90 |
| MAAGRE001 | ARENA | M3 | 0.536000 | $64.29 | $34.46 |
| MAAGRE003 | GRAVA | M3 | 0.650000 | $235.00 | $152.75 |
| MAAGU001 | AGUA (MANEJO) | M3 | 0.263000 | $10.00 | $2.63 |
| Suma de Material | $727.74 | ||||
| Equipo | |||||
| EQREV001 | REVOLVEDORA PARA CONCRETO DE 1 SACO MOD. R-10 | HR | 0.533300 | $52.97 | $28.25 |
| Suma de Equipo | $28.25 | ||||
| Costo Directo | $755.99 |