| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA DE MADERA | CIMBRA DE COMUN | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY16 MM | CIMBRAPLAY DE 16MM EN M2 | M2 | 0.180000 | $96.00 | $17.28 |
| MADERA DE PINO 3A | MADERA DE PINO 3A | PT | 3.000000 | $7.50 | $22.50 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.250000 | $13.17 | $3.29 |
| ANDAMIOS | ANDAMIOS | R/D | 0.040000 | $45.00 | $1.80 |
| DIESEL | DIESEL | LT | 0.400000 | $5.20 | $2.08 |
| Suma de Material | $46.95 | ||||
| Mano de Obra | |||||
| CUAD OC 08 | CUADRILLA OC 08 (1 OF. CARPINTERO O.N. + 1AYTE.) | JOR | 0.083333 | $678.12 | $56.51 |
| Suma de Mano de Obra | $56.51 | ||||
| Costo Directo | $103.46 |