| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA DE MADERA | CIMBRA DE MADERA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA-04 | MADERA DE PINO | PT | 3.000000 | $7.00 | $21.00 |
| A4EAR020 | Clavo c/cabeza de 2"-4" | kg | 0.250000 | $16.00 | $4.00 |
| ANDAMIOS | ANDAMIOS | R/D | 0.040000 | $45.00 | $1.80 |
| DIESEL | Diesel | LT | 0.400000 | $5.20 | $2.08 |
| Suma de Material | $28.88 | ||||
| Mano de Obra | |||||
| CUAD OC 08 | CUAD. 8 (1 OF. CARPINTERO O.N. + 1AYTE.) | JOR | 0.083333 | $747.85 | $62.32 |
| Suma de Mano de Obra | $62.32 | ||||
| Costo Directo | $91.20 |