| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 3.000000 | $16.15 | $48.45 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.100000 | $34.00 | $3.40 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| Suma de Material | $57.49 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.010000 | $290.45 | $2.90 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.100000 | $233.90 | $23.39 |
| AYUDANTE OPERADOR 1 | AYUDANTE OPERADOR | JOR | 0.100000 | $186.17 | $18.62 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.050000 | $169.01 | $8.45 |
| Suma de Mano de Obra | $53.36 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $53.36 | $1.60 |
| Suma de Herramienta | $1.60 | ||||
| Costo Directo | $112.45 |