| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PRIMARIO ANTICORROSI | PRIMARIO ANTICORROSIVO SYLPYL 53 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PRIM SYLPYL 53 | PRIMARIOANTICORROSIVO SYLPYL 53 INCLUYE FLETE A XALAPA | LT | 0.283150 | $68.53 | $19.40 |
| REDUCTOR. | REDUCTOR SOLVENTE | LT | 0.070700 | $13.00 | $0.92 |
| Suma de Material | $20.32 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 OFICIAL PINTOR + 2 AYUDANTES) | JOR | 0.021000 | $909.39 | $19.10 |
| Suma de Mano de Obra | $19.10 | ||||
| Equipo | |||||
| COMPRESOR | EQUIPO PARA APLICAR PINTURA | HR | 0.021000 | $104.97 | $2.20 |
| EQUIPO DE PINTURA.. | AIRLESS | HR | 0.117400 | $9.99 | $1.17 |
| Suma de Equipo | $3.37 | ||||
| Costo Directo | $42.79 |