| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 030506 | FABRICACION DE ESTRUCTURA EN ACERO ESTRUCTURAL A-36, FORMADA CON PERFILES Y LAMINADOS Y TUBERIA DE ACERO GAL.CED.40 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0088-11 | ACERO ESTRUCTURAL A-36 | KG | 10.400000 | $17.20 | $178.88 |
| 0088-11-13 | TUBERIA DE ACERO GALV.CED.40 | KG. | 15.080000 | $25.50 | $384.54 |
| 0088-11-15 | TORNILLOS DE 1"X20 CM CON TUESCA GAL. | PZA | 1.600000 | $18.00 | $28.80 |
| 1551-30 | SOLDADURA E-70-18 DE 1/8" | KG | 1.210000 | $40.00 | $48.40 |
| 2600-95 | PINTURA ANTICORROSIVA ( PRIMER ) COMEX | LT | 0.485710 | $35.00 | $17.00 |
| 2701/83 | PINTURA P.A.B. ESMALTE ALQUIDALICO COLOR GRIS CLARO | LTS | 0.500000 | $44.00 | $22.00 |
| Suma de Material | $679.62 | ||||
| Mano de Obra | |||||
| 02-0780 | CUADRILLA No 78 ( 1 SOLDADOR + 2 AYUDANTES DE SOLDADOR ) | JOR | 0.100000 | $952.79 | $95.28 |
| Suma de Mano de Obra | $95.28 | ||||
| Equipo | |||||
| 03-4240 | PULIDORA BLACK AND DECKER 4000 R.P.M. | Hora | 10.000000 | $0.51 | $5.10 |
| 03-4210 | SOLDADOR DE ARCO ELECTRICO MILLER MODELO M1250 CD TRANSFORMADOR RECTIFICADOR | Hora | 0.033650 | $1.18 | $0.04 |
| Suma de Equipo | $5.14 | ||||
| Costo Directo | $780.04 |