| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.5CON | CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL AGREGADO MAXIMO 40MM., FABRICADO EN OBRA EN REVOLVEDORA DE 1 SACO, ACARREO MATERIAL PRIMERA ESTACION=20.00M | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGR01 | ARENA (MATERIAL PÉTREO) | M3 | 0.460100 | $79.66 | $36.65 |
| AGR03 | GRAVA CRIBADA DE 1 1/2" | M3 | 0.729700 | $163.08 | $119.00 |
| AG | AGUA EN PIPA | M3 | 0.224440 | $51.50 | $11.56 |
| C03 | CEMENTO PORTLAND GRIS SACO | TON | 0.402700 | $2,097.00 | $844.46 |
| Suma de Material | $1,011.67 | ||||
| Mano de Obra | |||||
| ZCUAD3 | CUADRILLA (CONFORMADA POR 5 PEONES) | JOR | 0.066667 | $2,380.40 | $158.70 |
| Suma de Mano de Obra | $158.70 | ||||
| Equipo | |||||
| 25MAQ | Revolvedora ARSI:AR-10EK 1 saco de 8 hp mot. Kohler s/reductor | Hora | 0.533333 | $104.85 | $55.92 |
| Suma de Equipo | $55.92 | ||||
| Costo Directo | $1,226.29 |