| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2010 | CIMBRA COMUN EN CONTRATRABES Y TRABES DE LIGA EN CIMENTACION A BASE DE CIMBRAPLAY Y MADERA DE PINO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-MAD 22 | CIMBRAPLAY 16 MM | M2 | 0.200000 | $105.00 | $21.00 |
| OC-MAD 21 | CHAFLAN 1" | ML | 1.660000 | $6.15 | $10.21 |
| OC-CLAVO | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.166500 | $20.87 | $3.47 |
| OC-ACERO-01 | ALAMBRE RECOCIDO | KG | 0.500000 | $19.13 | $9.57 |
| OC-SEPARADORES | Separadores | PZA | 3.000000 | $2.50 | $7.50 |
| OC-COMB-002 | DIESEL | LT | 0.600000 | $7.24 | $4.34 |
| OC-MAD 004 | MADERA DE PINO DE 3A. | PT | 5.200000 | $11.50 | $59.80 |
| Suma de Material | $115.89 | ||||
| Mano de Obra | |||||
| OC-CUA4 | CUADRILLA (1 CARP. OBRA NEGRA + 1 AYUD.) | JOR | 0.100000 | $1,117.11 | $111.71 |
| Suma de Mano de Obra | $111.71 | ||||
| Costo Directo | $227.60 |