| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO PORTLAND ORD | Cemento Portland ordinario color gris | ton | 0.279000 | $1,617.20 | $451.20 |
| ARENA | ARENA | m3 | 0.542000 | $157.63 | $85.44 |
| GRAVA | GRAVA | m3 | 0.656000 | $160.00 | $104.96 |
| AGUA | AGUA | M3 | 0.325200 | $40.00 | $13.01 |
| Suma de Material | $654.61 | ||||
| Mano de Obra | |||||
| CUA OP EQUIPO 7 | CUAD. 1 OP. DE EQUIPO + 7 PEONES | jor | 0.055000 | $2,476.05 | $136.18 |
| Suma de Mano de Obra | $136.18 | ||||
| Equipo | |||||
| AREVOLVEDORA | REVOLVEDORA 8 H.P | hora | 0.666000 | $70.26 | $46.79 |
| Suma de Equipo | $46.79 | ||||
| Costo Directo | $837.58 |