| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 11800-02 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4", ELABORADO CON REVOLVEDORA. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARENA | ARENA | M3 | 0.536000 | $75.00 | $40.20 |
| CEMENTO DD | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.326000 | $1,582.61 | $515.93 |
| GRAVVVA | Grava de 3/4" | m3 | 0.650000 | $173.91 | $113.04 |
| AGUA | AGUA | M3 | 0.263000 | $25.50 | $6.71 |
| Suma de Material | $675.88 | ||||
| Mano de Obra | |||||
| CUAD OC 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.066667 | $1,892.05 | $126.14 |
| Suma de Mano de Obra | $126.14 | ||||
| Equipo | |||||
| AEEC012 | REVOLVEDORA DE CONCRETO CAPACIDAD DE 1 SACO 8 HP MOTOR MPOWER-JOPER | HORA | 0.533333 | $48.27 | $25.74 |
| Suma de Equipo | $25.74 | ||||
| Costo Directo | $827.76 |